- In the Batken region, the implementation of measures for the modernization and repair of electrical networks has begun, timed to prepare for the autumn-winter period of 2026-2027. This information was provided by the press service of the Batken Electric Networks Enterprise.

According to the enterprise's data, major repairs will affect 284 transformers with a voltage of 6–10/0.4 kV, while 1,632 transformers will undergo maintenance.

Work is also planned for overhead power lines. Major repairs will be carried out on 1,538 km of lines with a voltage of 6–10/0.4 kV, while 3,847 km of lines will undergo maintenance.

As for high-voltage lines with a voltage of 220/110/35 kV, plans include surveying 1,400 km of networks, of which 20 km will receive major repairs, and 1,380 km will undergo current repairs. In addition, 8,772 new glass insulators will be installed.

Repair work will also affect substations: 45 of them are expected to undergo planned current repairs, while five will undergo major repairs.

As part of the automation of the electricity transmission system, the installation of 54,587 smart metering devices (ASCUED) is planned in the Batken region in 2026. Additionally, in some settlements, 32 km of self-supporting insulated wires SIP-2 and SIP-3 will be laid.