In 2026, 1400 km of power lines will be upgraded in the Batken region.
It is planned to carry out major repairs on 20 km of lines, while scheduled maintenance will cover 1380 km of overhead lines. These works are aimed at preparing for the autumn-winter period of 2026–2027 and will be implemented in stages from March to November in the Kadamjai, Leilek, and Batken districts.
At the moment, as noted by the department, scheduled work has begun on the Sulukhtin section of the high-voltage lines on the routes "Khoja-Bakirgan – Arka" and "Arka – Morskaya," with a total length of 7 km. During these works, 190 old insulators will be replaced.
Note:
In 2025, the high-voltage overhead lines service of the Batken Electric Networks Enterprise completed a full replacement of 7200 old insulators on the 220/110/35 kV overhead lines, as well as the installation of 7513 new glass insulators. Scheduled maintenance covered 1264.75 km of high-voltage lines, while major repairs affected 134.6 km.
Read also:
In Batken, 1400 km of high-voltage overhead lines will be covered by repair works
In the Batken branch of OJSC "NES of Kyrgyzstan," a comprehensive repair of high-voltage...
In Batken Region, major and scheduled repairs of overhead lines have begun
In the Batken region, large-scale work is beginning on the repair of overhead power lines, which...
Без изображения
In the Batken Region, 400 km of 220/110/35 kV power transmission lines will be repaired.
In the Batken region, the repair of 400 km of power transmission lines with a voltage of 220/110/35...
In the Batken Region, a major renovation of 22 substations will be carried out
This year, major works are planned at 22 substations with voltages of 220/110/35 kV in Batken, as...