In the Issyk-Kul Region, 75.5 km of outdated power lines will be replaced
The replacement of the wires will affect several settlements and districts. In particular, the updates are planned in Karakol (8.6 km), Cholpon-Ata (19.7 km), Balakchy (5.6 km), Ton District (20 km), Ak-Suu District (6 km), Jeti-Oguz District (5.5 km), and Tyup District (7.7 km).
As part of the infrastructure upgrade, 1100 old wooden poles will be replaced with reinforced concrete ones. The work is set to begin in March 2026 and should be completed by November.
Additionally, in 2026, the construction of 27.1 km of new power transmission lines using SIP wires and the installation of 588 reinforced concrete poles are planned. Currently, 11 km of SIP lines have already been laid and 167 poles installed.
It is worth noting that in 2025, 90 km of SIP lines were laid in the Issyk-Kul region, and 1300 old wooden poles were replaced with new reinforced concrete ones. Most of the replaced poles were installed in the 1960s and 1970s and have long exceeded their service life, being in an emergency state.
Read also:
Без изображения
In the Issyk-Kul region, 2000 reinforced concrete supports will be installed in 2026, - Issyk-Kul PES
- In 2026, as part of the upgrade of electrical networks in the Issyk-Kul region, more than 2000...
In the Issyk-Kul region, more than two thousand emergency power poles will be replaced in 2026.
In seven distribution electrical networks, old wooden poles will be replaced with modern...
In the Issyk-Kul region, 2,000 new reinforced concrete supports will be installed
This year, work will continue in the Issyk-Kul region on the modernization of electrical networks....
Ministry of Energy: 2000 new reinforced concrete poles will be installed in the Issyk-Kul region in 2026
In 2026, work will continue in the Issyk-Kul region to update the electrical networks. The...
Ministry of Energy: 150 kilometers of SIP cable will be laid in Chui region in 2025
In 2025, more than 150 kilometers of SIP cables were laid and reconstructed by the Chui Electric...
In the Issyk-Kul region, over 75% of subscribers have switched to "smart" meters
In 2025, 45,396 "smart" meters were installed in the Issyk-Kul region, as reported by...
Без изображения
In the Issyk-Kul Region, 50 km of power lines will be upgraded and 14 substations will be installed in 2026.
- In 2026, the replacement of 50 kilometers of old electrical wires with modern self-supporting...