The discussion also involved the leadership of the Ministry of Transport and Communications, representatives of the national company "Kyrgyz Temir Zholu," and employees of the railway company "China - Kyrgyzstan - Uzbekistan."
Photo from the website of the Cabinet of Ministers of the Kyrgyz Republic.

Photo from the website of the Cabinet of Ministers of the Kyrgyz Republic.
Photo from the website of the Cabinet of Ministers of the Kyrgyz Republic.
As of March 26, the main project documentation is ready, and the drawings are currently being clarified and approved. Active work is underway at the construction sites: more than 5,600 units of equipment and over 5,000 workers are involved in the project. The main efforts are focused on tunnels, earthworks, and bridges. To date, more than 3.5 million cubic meters of earthworks have been completed.