How is the construction of the China - Kyrgyzstan - Uzbekistan railway progressing?

Наталья Маркова Politics
VK X OK WhatsApp Telegram
How the construction of the railway China - Kyrgyzstan - Uzbekistan is progressing
At a meeting with representatives of the company implementing the project, Minister of Water Resources, Agriculture, and Processing Industry Erlis Akunbekov discussed the progress of the railway construction. The government press service reported this.

The discussion also involved the leadership of the Ministry of Transport and Communications, representatives of the national company "Kyrgyz Temir Zholu," and employees of the railway company "China - Kyrgyzstan - Uzbekistan."

Photo from the website of the Cabinet of Ministers of the Kyrgyz Republic.



Photo from the website of the Cabinet of Ministers of the Kyrgyz Republic.

Photo from the website of the Cabinet of Ministers of the Kyrgyz Republic.

As of March 26, the main project documentation is ready, and the drawings are currently being clarified and approved. Active work is underway at the construction sites: more than 5,600 units of equipment and over 5,000 workers are involved in the project. The main efforts are focused on tunnels, earthworks, and bridges. To date, more than 3.5 million cubic meters of earthworks have been completed.

The photo on the main page is for illustrative purposes: akchabar.kg.
VK X OK WhatsApp Telegram

Read also: