"The National Electric Grid of Kyrgyzstan" will purchase 268 transformers
According to information from the Ministry of Energy, in 2026, the Open Joint Stock Company "National Electric Network of Kyrgyzstan" plans to purchase 268 transformers to ensure reliable electricity supply to the population.
As part of the preparation for the autumn-winter season of 2026–2027, work is planned to modernize substations in various regions of the country to increase their capacity.
At 20 substations of high-voltage lines with voltages of 35 and 110 kV, the capacity of transformers will be increased by 256 MVA.
The distribution of transformers by regions is as follows:
• Bishkek — 2 units;
• Jalal-Abad Region — 5 units;
• Issyk-Kul Region — 5 units;
• Naryn Region — 2 units;
• Talas Region — 2 units;
• Chui Region — 4 units.
In addition, to improve service quality and stability of electricity supply in 10/0.4 kV networks, 248 transformers will be installed and modernized, which will allow an additional increase in capacity of 107 MVA.
The distribution of new transformers will be as follows:
• Bishkek — 46 units;
• Osh Region — 46 units;
• Talas Region — 42 units;
• Jalal-Abad Region PES — 29 units;
• Issyk-Kul Region — 28 units;
• Naryn Region — 27 units;
• Batken Region — 22 units;
• Chui Region — 8 units.
These measures will allow for the renewal of equipment in the industry and reduce the load on electrical networks. The Open Joint Stock Company "NESC" will continue its work on modernizing the energy system in accordance with current requirements, as emphasized in the Ministry of Energy's statement.
If you have any questions regarding electricity supply, you can contact the 24-hour call center of the Open Joint Stock Company "NESC":
• 105 (toll-free call)
• Phones: +996 772 001209, +996 556 001209
• WhatsApp: +996 702 001209
Read also:
Без изображения
"NESK" will purchase 268 transformers in 2026
- In 2026, OJSC "National Electric Network of Kyrgyzstan" plans to acquire 268...
Без изображения
"NESK" installed and increased the capacity of 645 transformers on 10/0.4 kV lines in 2025
- Kyrgyzstan National Electric Network 12:10 (9 minutes ago)...
Due to the anticipated frosts, energy companies have intensified control over the power grids.
In connection with the expected cold weather, the Ministry of Energy has announced an increase in...
Ministry of Energy: 150 kilometers of SIP cable will be laid in Chui region in 2025
In 2025, more than 150 kilometers of SIP cables were laid and reconstructed by the Chui Electric...
Limits, power reduction, and imports. How winter is going for energy workers
Winter is nearing its end, and the heating season of 2025/26 is coming to a close. The beginning...