The capacity of 32 transformers will be increased in Talas, and 10 additional ones will be installed.

Марина Онегина Exclusive
VK X OK WhatsApp Telegram
The capacity of 32 transformers will be increased in Talas, and 10 additional ones will be installed

In 2026, the Talas electric grid enterprise has planned a series of activities aimed at improving the reliability of electricity supply and preparing for the cold season. In particular, the plans include increasing the capacity of 32 transformers and installing 10 new devices, according to information from the Ministry of Energy of Kyrgyzstan.

Regarding the installation of new transformers, they will be distributed across the Talas region as follows:


It is worth noting that in 2025, 9 transformers were already added in the region.
Considering the growing demand for electricity, in 2026, the capacity of 32 transformers will also be increased, distributed as follows:


In 2025, the capacity of 13 transformers in the district was already increased.
Additionally, as part of the standard annual maintenance and major repair work on transformers, the following is planned for 2026:



The implementation of these activities should lead to increased reliability of electrical networks, a reduction in the number of emergency outages, and provide the population with stable and quality electricity supply.
Contact information for inquiries regarding electricity supply:

105 (toll-free)

+996 772 001 209

+996 556 001 209

WhatsApp: +996 702 001 209
VK X OK WhatsApp Telegram

Read also: