In Naryn Region, 21 transformers will be replaced and an additional six units will be installed in 2026.

Елена Краснова Exclusive
VK X OK WhatsApp Telegram
In Naryn region, 21 transformers will be replaced and six additional units will be installed in 2026

In the Naryn region, the replacement of 21 transformers is planned for 2026, distributed across the districts as follows:

• 1 transformer will be installed in the Ak-Tal district;

• 3 in the At-Bash district;

• 7 in the Kochkor district;

• 7 in the Naryn district;

• 3 in the Toguz-Toro district.

In addition, it is planned to place 6 new transformers:

• 1 in the At-Bash district;

• 2 in the Jumgal district;

• 3 in the Naryn district.

According to the Ministry of Energy, the program for capital and current repairs includes 2,015 transformers.

In 2025, the Naryn electric grid enterprise replaced and installed 83 transformers, including:

• 61 transformers with a voltage of 10/0.4 kV were replaced;

• 22 transformers with the same voltage were additionally installed.

These actions allowed for an increase in total electrical capacity by 39,217 kVA compared to the previous year.

Furthermore, 121 transformers were transferred to the balance of the Naryn electric grid enterprise. All measures are aimed at providing residents with quality and stable electricity supply.