Roof Collapse at a School in the Tyup District. How the Contractor Was Punished
As is known, the collapse occurred on the night of January 18, 2026, due to heavy snowfall.
The construction of the new school, designed for 150 students, began in 2023. The project was built with the support of the charitable foundation "As-Salam," and the contractor was the company OsOO "Energy-Nur Stroy."
Currently, the school has not yet been put into operation, as at the final stage, during the roof installation, the project was not accepted by the Issyk-Kul Regional Department of the State Architectural and Construction Control (Department).
Previously, the Department had repeatedly sent warnings to OsOO "Energy-Nur Stroy" regarding issues related to the construction of the school.
As a result of the incident, the Department issued a written warning to the contracting organization and demanded the restoration of the project.
As of today, the roof of the school has been fully restored. The contractor has been fined 200,000 soms, and the issue of suspending its license will be considered at the commission meeting.
After the necessary inspections by the authorized bodies and receiving a positive conclusion, the Issyk-Kul Regional Department of Architectural and Construction Control will officially put the project into operation.
Read also:
Без изображения
At Issyk-Kul, the roof of a school under construction collapsed after a snowfall
The Ministry of Construction, Architecture, and Housing and Communal Services of Kyrgyzstan...
The Ministry of Construction of Kyrgyzstan clarified the situation regarding the collapse of part of the roof of a new school in the Tyup District
The school has not yet been put into operation, as at the stage of completion of construction,...
Без изображения
The roof collapsed at the school being built in Issyk-Kul. Comment from the Ministry of Construction
In the Issyk-Kul region, in the village of Min-Bulak, part of the roof of a school being built by...
Без изображения
"Ai-Pery" has transformed into an international business center — photo report
Curl error: Operation timed out after 120000 milliseconds with 0 bytes received...