Work is underway on the reconstruction of the Bishkek—Kuntuu—Shopokov highway, - Ministry of Transport
Curbs are currently being installed on the section of the road measuring 0–3.9 km. In Kuntuu, preparatory work is underway for laying asphalt on the sidewalks.
Additionally, the roadbed is being strengthened on the segment from Kuntuu to Tokbay, where embankments are being created. On the section from Tokbay to Kara-Sakala, land clearing is being carried out, including tree cutting.
This project is being implemented as part of the "State Capital Investments" and is being carried out by the Road Construction Administration No. 1 (DGU No. 1) of the state enterprise "Kyrgyzavtozhol-North".
Additional information:
The length of the road is 12.4 km. The first layer of asphalt concrete was laid on a section of 6.7 km in 2025.
The current project includes widening the road to four lanes, creating sidewalks, installing modern lighting, and planting new trees to replace those that were cut down.
Read also:
Reconstruction of the Bishkek - Kuntuu - Shopokov Road: Expansion of the Second Half of the Highway Has Begun
The reconstruction of the Bishkek - Kuntuu - Shopokov road is actively ongoing, according to...
The Bishkek–Kuntuu–Shopokov road will be expanded to four lanes
The reconstruction of the Bishkek–Kuntuu–Shopokov road is currently underway, during which the...
Без изображения
Road Bishkek - Kuntuu - Shopokov. What is the status of the reconstruction?
Starting from February 23, work has begun on a 6.7 km section of the Bishkek - Kuntuu - Shopokov...