In the Talas Region, 1158 reinforced concrete supports will be installed

Ирина Орлонская Society / Exclusive
VK X OK WhatsApp Telegram



According to information from the Ministry of Energy, from March to November 2026, 1158 reinforced concrete poles will be installed in the Talas region. These works are planned as part of a project for the construction and reconstruction of overhead power lines with a voltage of 0.4-10 kV.

In particular, in the Bakai-Ata district, the installation of 257 poles is planned, of which 7 will be new for the 10 kV line, while 250 poles will be replaced during the reconstruction of the 0.4-10 kV lines.

In the Manas district, 228 poles will be installed: 65 of them will be new for 10 kV, and 163 poles will be replaced during the reconstruction of 0.4-10 kV.

The Aitmatov district will receive 316 poles, of which 12 will be new for 10 kV, and 304 poles will be replaced as part of the reconstruction of 0.4-10 kV.

In the Talas district, 302 poles are also planned for installation. Of these, 164 will be new for 0.4-10 kV, and 138 poles will be replaced during the reconstruction.

In the city of Talas itself, 55 poles will be installed, among which 17 will be new for 0.4 kV, and 38 poles will be replaced during the reconstruction of the 10 kV overhead line.