In the Jalal-Abad Region, 555 transformers will be repaired and 14 new ones will be installed.

Елена Краснова Society / Exclusive
VK X OK WhatsApp Telegram



In the Jalal-Abad region, it is planned to repair 555 transformers with a voltage of 6–10/0.4 kV and install 14 new devices, as reported by the Ministry of Energy.
The work will begin in March and last until November 2026. During the repair process, the technical condition of the transformers will be assessed, worn components will be replaced, and necessary maintenance will be performed.
The introduction of new transformers into operation will significantly improve the quality of electricity transmission, help balance loads, and ensure reliable power supply for consumers.

The repair and installation of new transformers will be carried out in the following settlements:

- Aksy District — 55 transformers under repair, 1 new;

- Ala-Buka District — 67 transformers under repair, 1 new;

- Bazar-Korgon District — 41 transformers under repair, 2 new;

- Manas City — 24 transformers under repair, 2 new;

- Kara-Kul City — 19 transformers under repair, 1 new;

- Kok-Art Valley — 53 transformers under repair, 1 new;

- Mailuu-Suu City — 10 transformers under repair, 1 new;

- Nooken District — 71 transformers under repair, 2 new;

- Suzak District — 81 transformers under repair, 2 new;

- Toktogul District — 92 transformers under repair, 1 new;

- Tash-Kumyr City — 28 transformers under repair;

- Chatkal District — 14 transformers under repair.

There are 4,348 transformers on the balance sheet of the Jalal-Abad Electric Networks Enterprise. It is expected that by the end of the year, all of them will undergo maintenance and repair. The project is financed by JSC "NESC" and implemented by the Jalal-Abad Electric Networks Enterprise.