The area of the new airport terminal in Osh will be 26,000 square meters - video
According to the department, 95% of the monolithic works have been completed, and 80% of the installation works for the engineering systems in the underground part of the building have also been finished. These systems include electricity supply, ventilation, water supply, sewage, and fire-fighting water supply. However, work on the first floor has been temporarily suspended due to the need for adjustments to the project documentation.
The minister emphasized the importance of completing the construction on time and with high quality, promptly making all necessary changes to the project, as well as increasing the pace of work by increasing the number of employees. Currently, about 120 workers are involved in the construction, but it is planned to double this number in the future.
It is worth noting that the construction work started on April 25, 2025.
Read also:
At what stage is the construction of the new terminal complex of Osh Airport?
Last week, the Minister of Construction, Architecture, and Housing and Communal Services, Nurdana...
Без изображения
Minister Oruntaev checked the progress of construction of the new terminal complex at Osh Airport
- During his working trip to Osh, Nurdin Oruntaev, the Minister of Construction, Architecture, and...