Minister Oruntaev checked the progress of construction of the new terminal complex at Osh Airport
The area of the new terminal is 26,000 square meters and includes six construction blocks: A1, A2, B1, B2, C1, and C2. Construction began on April 25, 2025, and about 120 workers are employed at the site.
As of February 26:
the monolithic works are 95% complete.
the installation of engineering communications in the basement, including power supply, ventilation, drainage, and fire-fighting water supply systems, is 80% complete.
Work on the first floor has been temporarily halted due to the need for changes to the project documentation.
Read also:
At what stage is the construction of the new terminal complex of Osh Airport?
Last week, the Minister of Construction, Architecture, and Housing and Communal Services, Nurdana...
Без изображения
Declaration-2024. How much did the head of the Ministry of Construction Nurdin Oruntaev earn and what do his deputies own?
- In 2025, the agency previously known as the State Agency for Architecture, Construction, and...
Nurdin Oruntaev gave instructions for checking the activities of LLC "Elit-Stroy-City"
Recently, Nurdin Oruntaev, the Minister of Construction, Architecture, and Housing and Communal...