The Batken Electric Networks Enterprise has completed major repairs on 3 substations, - NESK
As part of the work, significant repair activities were carried out at the 35/10 kV substations "Kara-Tokoy-2", "Ak-Turpak", and 35/6 kV "Shirech".
During the repairs, the transformers underwent a complete technical inspection, and outdated equipment was replaced. Additionally, to enhance the reliability of electricity supply, the relay protection and automation systems were checked, and necessary repair work was carried out.
Furthermore, sanitary and cleaning works were conducted at the substation sites, and the facilities were brought into compliance with safety requirements.
Read also:
In the Batken Region, a major renovation of 22 substations will be carried out
This year, major works are planned at 22 substations with voltages of 220/110/35 kV in Batken, as...