In 2026, extensive construction and reconstruction work is planned in the Osh region. According to information from the Ministry of Energy of Kyrgyzstan, 134.64 km of overhead power lines will be updated and constructed using self-supporting insulated wires (SIP).
The use of modern SIP will significantly improve the quality of electricity supply, reduce the number of emergency outages, and decrease technical losses in the network.
The following work is planned for 2026:
- Construction of a new 10 kV overhead line — 16.33 km
- Reconstruction of a 10 kV overhead line — 50.67 km
- Construction of a new 0.4 kV overhead line — 15.3 km
- Reconstruction of a 0.4 kV overhead line — 52.34 km
According to representatives of the Ministry of Energy, these measures will provide the residents of the Osh region with reliable, high-quality, and safe electricity supply. The work will begin in March and last until November, allowing for preparation for the autumn-winter period.
Further modernization of the energy infrastructure is planned for the future.
For any questions regarding electricity supply, you can contact the 24-hour call center:
Call center: 105; 1209
0772001209
0556001209
Call center: 105; 1209
0772001209
0556001209
Initially, information about the update and construction of 134.64 km of SIP lines in the Osh region appeared on the K-News website.