Currently, the following stages of work have been completed:
- A temporary access road 8 km long has been laid to the construction site;
- A plot of land has been allocated for the construction of a water intake at the bottom of the Papan reservoir;
- Technical conditions for the use of electricity during the construction process have been developed and approved.
Photo courtesy of the press service of the Ministry of Energy of the Kyrgyz Republic.
Photo courtesy of the press service of the Ministry of Energy of the Kyrgyz Republic.
Photo courtesy of the press service of the Ministry of Energy of the Kyrgyz Republic.
In addition, the process of land allocation and transformation is currently underway to create a production complex that includes the hydropower plant building and an open switchgear with a voltage of 110 kV. Questions are also being considered regarding the use of land for the installation of supports for the overhead power line VL-110 kV from the Papan Hydroelectric Power Station to the "Uzlova - Besh-Moinok" line.
Furthermore, work is ongoing on the design and estimate documentation, a preliminary construction schedule has been approved, and permits for access to the Papan reservoir area have been obtained, while engineering surveys continue, the press service reports.
The capsule-laying ceremony for the Papan Hydroelectric Power Station took place on October 5, 2024.