The city hall explained why the repair of Bakayev Street has been delayed.
He noted that the city hall has been receiving complaints from citizens that the project has been delayed for three years. The work on the extension of Bakayev Street began in November 2024. Last year, the work was almost completed, but difficulties arose with the relocation of utilities.
This section contained heating networks, which were successfully relocated. However, two gas lines created additional difficulties. "Gazprom" needed time to develop and approve the project, which also extended the work period by a year. Now that "Gazprom" has completed its work, paving will begin with the warming, and the project will be completed this year," Janbolotov added.
The Deputy Director also noted that the relocation of gas lines is not the only problem faced by the road workers. There are difficulties with drainage. Currently, a sewer system is being constructed for drainage, which should connect to the Ala-Archa River.
Janbolotov added that clearing the area has become a problem, as several plots were transferred to private ownership in 2022, and there is a "red book." "We explain that we must continue the work. Some claim that this section is pointless. But I want to emphasize: the street will be extended from Bokonbaev Street with the construction of a bridge over the Ala-Archa River and will connect to Beyshenalieva Street," he noted.
Additionally, he reported that the reconstruction work on the southern side of Dän Xiaoping Avenue, L. Tolstoy Street - from Termechikova Street to Frunze Street, and Auezov Street - from Jibek Jolu Avenue to Salieva Street has been postponed to 2026.
Read also:
Без изображения
Why the construction of Bakayev Street in Bishkek has been delayed, explained the official
In Bishkek, work will continue on the repair of streets that were not completed in 2025. This was...