According to information provided by the Ministry of Energy of Kyrgyzstan, OJSC "Chakan HPP" has already completed about 80% of the construction work on the Orto-Tokoy HPP. Construction is actively continuing according to the established schedule.
Among the completed stages:
the 950-meter long diversion tunnel is fully ready;
concreting of the water supply tunnel is underway;
preparatory work and soil reinforcement have been carried out, and the walls of the chamber at the branching node have been constructed;
installation of the tunnel interchange with three exits is being prepared: metal structures with a length of 93.6 meters have already been installed in one of the exits, and 74.4 meters in another.
construction of the HPP building is 90% complete;
reinforcement and concreting of columns for the lifting mechanisms of the spillway gates of the lower reach have been completed;
the roof frame installation has been completed, and work on laying the roofing material is ongoing;
installation of hydro turbines No. 1, 2, and 3, as well as disk gates, has been successfully completed.