Preparation for the launch of the second hydro unit of the Kambar-Ata HPP-2. What has already been done

Наталья Маркова Economy
VK X OK WhatsApp Telegram
The project for the commissioning of the second hydro unit of the Kambar-Ata HPP-2 is being implemented with the support of the Eurasian Stabilization and Development Fund. An important role in the technical support of the project is played by the international consulting company Fichtner GmbH & Co. KG.

The work is divided into three lots, and based on the results of international tenders, contractors have been selected for each direction:

Current Achievements



Photo by the press service of JSC "Electric Stations".



Photo by the press service of JSC "Electric Stations".



Photo by the press service of JSC "Electric Stations".



Photo by the press service of JSC "Electric Stations".



Photo by the press service of JSC "Electric Stations".



Photo by the press service of JSC "Electric Stations".

Within the framework of the project, important stages have already been completed:

According to JSC "Electric Stations," constant monitoring of the project's progress is being carried out in collaboration with contractors and engineering consultants to ensure compliance with the approved deadlines for the completion of work.